Urgenc-Hiva, Bukhara and Semerkand Airports of Uzbekistan were upgraded to receive international flights as part of the modernization program which includes the following works / facilities: new terminal buildings, transformers and auxiliary facilities, runway rehabilitation, runway expansions, asphalt pavement that conforms to international flight standards. Length of the 3 runways that were constructed in each airport is 3200 meters.

 

Client Uzbekistan National Airlines

Location Uzbekistan

Contract Date 27 April 1997

Completion Date 29 May 1998

 

 