Köprübaşı Dam and HEPP, some part of which was constructed by General Directorate of State Water Works, is located in Bolu-Mengen region. The project is a Yüksel investment while the energy production and sales licence is hold by Yüksel Enerji Elektrik Üretim ve Ticaret A.Ş. that is valid for 49 years. Köprübaşı is one of the five underground power plants in Turkey.
Köprübaşı Dam is a clay cored rock-fill dam type having the installed capacity of 79 MW and annual electricity generation of 203 GWh.
Energy Generation has started in March 2012 and 140.768.090 kWh energy has been produced and sold in 2012.
License Holder Yüksel Power and Electricity Production and Trade, Inc.
Location Bolu-Mengen / Turkey
Contract Day 20 June 2007
License Duration 49 Years Completion Date: 05 March 2012
Last updated on 21st May, 2013