The Project involves construction of a 30 km motorway section accommodating 2X3 lanes (two way road). 6 no’s of reinforced concrete bridges of 1047 m long in total, with spans varying between 1 to 8 and pre-stressed and post-tensioned segmental (each beam made of 3 pre-stressed/pre-cast segment) launching girders. In addition, 7 over/underpasses and road junctions, tolling stations, maintenance center and parking areas are also included within the scope. The project was completed by a joint venture with the lead partnership of Yüksel.
Location Romanya