Mbamou Palace Hotel Construction & Renovation – Brazzaville

The investor of Mbamou Palace Hotel is Government of the Republic of Congo and contract type is “cost-plus-fixed fee”. The gross construction area of the building is approximately 21,000 sqm. and structural & façade cladding activities have previously been completed to a certain extent. Yüksel takes the responsibility of not only converting the existing facility to a five star hotel complex but also performing design studies, finishing works, mechanical-electrical installations, interior design and landscape activities. A contract modification to include a ballroom/restaurant structure along with underground parking facilities is expected to be executed very soon.

 

Client Anonim Congo Construction (ACC)

Location Brazzaville / Republic of the Congo

Contract Date 13 June 2014

Completion Date 01 August 2016